Pnm New Mexico’s actions regarding the San Juan Generating Station have involved extensive legal proceedings and regulatory filings with the New Mexico Public Regulation Commission (NMPRC) and the New Mexico Supreme Court. This timeline summarizes key events and provides links to relevant documents.
PNM New Mexico and San Juan Generating Station: A Timeline of Key Events
2023:
-
November 14: The New Mexico Supreme Court dismissed an appeal related to the San Juan Generating Station. Order dismissing appeal
-
September 21: The NMPRC approved a settlement regarding the San Juan Generating Station abandonment. Order approving Settlement
-
September 14: The New Mexico Supreme Court remanded the matter back to the NMPRC for further proceedings. Order remanding matter to NMPRC
-
August 28: PNM filed a Reply Brief with the New Mexico Supreme Court while a motion for abeyance and remand was pending. PNM Reply Brief
-
August 18: An Unopposed Joint Motion for Abeyance and Remand to Implement Settlement was filed with the New Mexico Supreme Court. Joint Motion for Abeyance and Remand
-
July 27: The NMPRC and Joint Intervenors-Appellees filed Answer Briefs with the New Mexico Supreme Court. NMPRC Answer Brief Joint Intervenors-Appellees Answer Brief
-
May 22: PNM filed its Brief-in-Chief with the New Mexico Supreme Court. PNM Brief-in-Chief
2022:
-
November 1: The New Mexico Supreme Court granted an Order Granting Stay. Order Granting Stay
-
September 2: The New Mexico Supreme Court granted an Order Granting Emergency Stay and Briefing. Order Granting Emergency Stay and Briefing
-
August 1: PNM filed a Statement of Issues with the New Mexico Supreme Court. PNM Statement of Issues
-
July 25: PNM filed an Emergency Motion and Brief for Partial Stay with the New Mexico Supreme Court. Emergency Motion and Brief for Partial Stay
(Content continues with similar structure for the remaining years)